Town Services > Road Construction and Repair


Road Commissioner:
Phone: (207) 848-3361
Hours: 9:00 AM – 5:00 PM Mon- Fri or by appointment

Roads Status

During 2006, the section of Horseback Road between Route 2 and the Fuller Road is scheduled to be ditched where needed, reclaimed and covered with 2” of new hot top. It is also hoped that we can ditch, reclaim and put 2” of new pavement on one mile of Cook Road from the Newburgh line towards Route 2. Much of what we are planning will be controlled by the price of petroleum. We hope to get our best possible price by going out to bid fairly early in the spring.

Water is the enemy of our roads. The wet spring and fall we had in 2005 and the warm and wet winter we have had in 2005 – 2006 have raised havoc with our streets.

Looking ahead to 2007, the Dyer Road and part of the Five Road need to be ditched, reclaimed and paved.